Category(ies):
Construction Horizontal: Highways & Roadways; Maintenance, Repair & New Construction - Construction Architectural, Engineering & Surveying - Commodities Construction Horizontal: Highways & Roadways; Maintenance, Repair & New Construction - Commodities Construction Horizontal: Highways & Roadways; Maintenance, Repair & New Construction - Consulting & Other Services |
Rose Road over Bower CreekDescription: Removal of Existing Bridge and replacement with a precast three-sided concrete frame structure supported on cast-in-place footings and associated highway approach work and stream work. Construction will be on the existing alignment with an off-site detour to maintain traffic during construction. Prevailing wage rates apply. Disadvantage Business Enterprise Utilization Goal: 5% EEO Minority Goal: 5.9% Women Participation Goad: 6.9% Bid Bond: 5% Due Date: 05/08/2025 2:00 PMContract Term: Duration 150 Days - no later than 11/21/25 Location: Rose Road over Bower Creek Ad Type: General
|